ΒιΆΉΤΌΕΔ

Asbestos Management on ΒιΆΉΤΌΕΔ premises

This is a summary of the way that asbestos is managed in ΒιΆΉΤΌΕΔ Buildings. It supplements the information about managing asbestos on productions.

Updated: 11 January 2022

What Can Go Wrong?

Asbestos in various forms has been used very widely in many building products, as a reinforcing fibre in many plastics and as an engineering product in applications such as brake linings. Its wide use stems from it being chemically inert, light and strong, and because it is very stable when exposed to heat.

Asbestos, inhaled as dust can cause Lung Disease (Asbestosis), Lung Cancer and Mesothelioma (a cancer associated only with exposure to Asbestos). People who smoke are at greatly increased risk.

Asbestos when incorporated into a solid material (concrete, bitumen, plastic) poses very little risk until that material suffers mechanical damage (being, cut, broken, drilled, sanded, exposed to extreme heat or explosion).

Workplace will decide if Asbestos needs to be removed. Asbestos will not normally be removed unless there is a danger of disturbing it during works or a danger of future disturbance.

Legal / ΒιΆΉΤΌΕΔ Requirements

  • Control measures with the words Must or Must Not are mandatory under ΒιΆΉΤΌΕΔ rules.
  • Control of Asbestos Regulations 2012.

Control Measures

General Controls

  • Asbestos in ΒιΆΉΤΌΕΔ Premises is managed by ΒιΆΉΤΌΕΔ Workplace, there is a detailed Asbestos Management Strategy that must be adhered to. You must employ the controls below
  • Report any suspected damage and / or any suspicious material which is not labelled to ΒιΆΉΤΌΕΔ Workplace Service Centre: Tel 0490 (internal); 0808 1688 962 (external).
  • Contact ΒιΆΉΤΌΕΔ Workplace Service Centre before conducting any work (building, fitting out, cable pulling, etc) on the fabric of the building. They will contact a specialist who will tell you if you need to have a survey carried out.
  • Check the Asbestos Register for the building if you are conducting work on the fabric.
  • You must not work on Asbestos Containing Material.
  • You must not work in any area where fibres are present above the clearance level.
  • Call ΒιΆΉΤΌΕΔ Safety / ΒιΆΉΤΌΕΔ Occupational Health if you are concerned you may have been exposed to asbestos (see our Contacts page in the top banner). See also our Safety Short "Health Information - Inadvertent Exposure to Asbestos" in Useful Documents.

Managers Controls

  • Managers must identify staff who might be at risk, arrange awareness training via Academy
  • For buildings where there is not a permanent Facilities Management presence the Manager with day to day responsibility for a building (for example the Managing Editor) must appoint β€œAppointed Person Asbestos” to hold a copy of the asbestos register for the building and to ensure that precautions are in place.

Emergency Arrangements

If you know or suspect that asbestos containing material has been disturbed the take the following action:

  • Move other people away from the vicinity.
  • Close doors if possible. 
  • Tell your manager. 
  • Contact ΒιΆΉΤΌΕΔ Workplace Service Centre: Tel 0490 (internal); 0808 1688 962 (external).
  • Email: bbcworkplace.servicecentre@interservefm.com
  • Report the incident on myRisks.

Role of Workplace

  • Appoints, manages, and monitors service partner to manage asbestos.
  • Manages relationship with third party landlords, tenants and occupiers of shared premises.
  • Via service partner:
  • Holds asbestos register.
  • Ensures information is acquired and passed on when buildings are acquired or disposed of.
  • Funds all asbestos works.
  • Manages incidents.

Role of ΒιΆΉΤΌΕΔ Safety

  • Advises on the investigation of incidents.
  • Keeps records of incidents.
  • Provides general advice.

Premises and sets topics

  • Sets & Premises safety guide

    This Safety Guide collates those of our Safety Guidelines relating to construction activities (on sets or other structures, including under 'CDM') and to the occupation / use of building premises (studios or locations).
  • This site is for ΒιΆΉΤΌΕΔ Employees or potential future employees only. If you are not a ΒιΆΉΤΌΕΔ employee or looking for further information regarding ΒιΆΉΤΌΕΔ Access Services then please click on another page from the menu above, where you can find out more about Remploy.
  • Asbestos Management on ΒιΆΉΤΌΕΔ premises

    This is a summary of the way that asbestos is managed in ΒιΆΉΤΌΕΔ Buildings. It supplements the information about managing asbestos on productions.
  • CDM Overview

    Legislation to ensure the safe design and construction of structures was updated in April 2015, namely the Construction (Design and Management) Regulations 2015 (CDM 2015)
  • CDM 2015 - The ΒιΆΉΤΌΕΔ Approach

    Guidance on the practical application of the Construction (Design and Management) Regulations 2015 across the ΒιΆΉΤΌΕΔ
  • First Aid in ΒιΆΉΤΌΕΔ Premises

    This page describes how first aid is arranged in ΒιΆΉΤΌΕΔ premises. It supplements the guidance to first aid on productions. It is aimed at people who need to decide what provision to make for first aid on ΒιΆΉΤΌΕΔ premises. It also provides the arrangements and numbers for contacting ambulances and the National Central Control Room (NCCR).
  • Legionella in Premises: Control of

    This guidance provides an overview of how water systems are managed in premises to minimise the risks from the Legionella bacteria.
  • Permit to Work in ΒιΆΉΤΌΕΔ Buildings (Restricted Work)

    Some work in ΒιΆΉΤΌΕΔ buildings is restricted and you have to get permission, called a Permit To Work (PtW) to do it.
  • Pressure Systems

    A guide to pressure systems in buildings. Pressure Systems include all plant/systems that contain a β€˜relevant fluid’, defined as steam or gas under pressure and liquids under pressure which become gases upon release to the atmosphere, at a pressure greater than 0.5 bar (about 7psi) above atmospheric (except for steam). Around the ΒιΆΉΤΌΕΔ there are heating, fuel transfer, compressed gas and hydraulic systems used in program production, studios (e.g. Camera Peds), office and maintenance facilities.
  • Sets: Safety of

    This Safety Guideline is concerned with the construction and use of production sets and associated scenery used in studios and on locations.

More from SSR

  • Your platform to record accidents, risk assessments, assurance monitoring and inspections
  • Safety Equipment Stores

    Just one number to call: 0844 800 8875
  • ΒιΆΉΤΌΕΔ Safety Guidelines

    An A-Z of ΒιΆΉΤΌΕΔ's Health and Safety Guidelines
  • Safety Advice Line: 0370 411 0464 Email: safety@bbc.co.uk

About this site

This site describes what the ΒιΆΉΤΌΕΔ does in relation to managing its health, safety and security risks and is intended for those who work directly for the ΒιΆΉΤΌΕΔ.

It is not intended to provide instruction or guidance on how third parties should manage their risks. The ΒιΆΉΤΌΕΔ cannot be held liable for how this information is interpreted or used by third parties, nor provide any assurance that adopting it would provide any measure of legal compliance. More information

Some links on this site are only accessible when connected to the ΒιΆΉΤΌΕΔ network

Rebuild Page

The page will automatically reload. You may need to reload again if the build takes longer than expected.

Useful links

Theme toggler

Select a theme and theme mode and click "Load theme" to load in your theme combination.

Theme:
Theme Mode: