The TMO conclude their evidence and the inquiry hears from expert witnesses Barbara Lane & Beryl Menzies
The TMO conclude their evidence and the inquiry hears from expert witnesses Dr Barbara Lane & Beryl Menzies.
Peter Maddison, former Director of Assets and Regeneration at the Kensington and Chelsea TMO said he knew meeting contractor Rydon before the conclusion of the tender process was a commercial risk but one worth taking. He also faced questions on the late submission of his diaries and notebooks.
Expert witness Beryl Menzies stated that RBKC Building Control made a fundamental failure by not asking for more details about the cladding material.
And expert witness Dr Barbara Lane said fire safety consultants Exova’s failure to analyse the cladding proposals amounted to professional negligence.
Presenter / Producer: Kate Lamble
Producer: Sharon Hemans
Researcher: Luke Radcliff
Editor: Hugh Levinson
Podcast
-
The Grenfell Tower Inquiry Podcast
A new 10-part series about the Grenfell Tower fire and why it happened